محطة ضخ 5

محطة ضخ 5
ClientAl Bunayat Al Arabiya – Darb Al Riyadh
OwnerNational Water Company
LocationQassim Region
ValueWithin the Mishash & Al Fuwayliq package totaling 30,530,936.00
Duration30 months
StatusCompleted
Scope of Work

Key Execution Responsibilities

Water pump station including civil, architectural, mechanical, electrical and control systems.

إجمالي المضخات4
مضخات الخدمة3
كمية التدفق140 م³/ساعة
الرفع185 م
قدرة المولد2 × 420 kW
سعة المحول800 kVA
الاستهلاك512 kWh
Project Summary

Execution Scope

Water pump station including civil, architectural, mechanical, electrical and control systems.

Workstreams

  • Technical and execution coordination on site.
  • Materials and approvals management as required.
  • Quality, safety and testing control.

Project Status

  • Completed project within the company previous-works record.
  • Project value, client and location are shown in the facts card above.
  • Project documentation and data are retained in the previous works record.